The retail fuel station project Jeff Masemola transformed an existing Shell service station into a fully operational Engen site at the corner of Jeff Masemola and Sisulu Roads in Pretoria.
The Engen Jeff Masemola project included new pump-and-tank infrastructure, forecourt and civil works, shop conversion, Café 365 coordination, canopy refurbishment, electrical and mechanical services, branded signage, compliance coordination and final handover.

ENGEN
Existing service station conversion and redevelopment
3 months
08/09/2025 – 09/12/2025
Theta Projects led the planning and delivery process across project management, architecture, construction coordination and specialist teams. Quantity surveying and cost control were handled through Theta QS, a company established by Theta Projects.
Theta Projects acted as the central coordination team and connected the design, cost, construction and specialist workstreams.
The Retail Fuel Station Project Jeff Masemola project involved a broad project team, including:
The work required service station project management Pretoria experience that could account for fuel infrastructure, a live urban site, Engen specifications, shop requirements, municipal processes and specialist certificates. Theta coordinated these parts as one project rather than treating the building, forecourt, fuel systems and brand conversion as unrelated packages.
Theta QS provided quantity surveying and project cost control.
Theta Projects was appointed:

The fuel infrastructure work included tank-farm excavation, underground tank installation, backfilling, fuel piping, trenching, pressure testing, automatic tank-gauging equipment, smart controllers and dispenser installation.
Project cost records identify two 46kl underground tanks and one 23kl underground tank, together with five six-hose dispensers. These specialist works formed a central part of the Engen Jeff Masemola project and had to be sequenced with the civil, electrical and forecourt programme.

The existing concrete forecourt was demolished to make way for the new fuel and site works. The civil scope included kerbing, paving, stormwater reinstatement, separator manhole covers, bollards and associated external works.
This part of the retail fuel station project Jeff Masemola had to support customer circulation, fuel deliveries, drainage, dispenser positions and the daily operation of the completed site. It is a clear example of why service station construction coordination starts with how the whole property must work once it reopens.

The existing convenience shop was converted to the Engen retail format, with THETA involved in shop design and coordination of the Café 365 requirements.
The recorded workstreams included shelving, electrical services, refrigeration, air-conditioning, kitchen extraction, bakery drainage, ventilation, point-of-sale equipment, computer equipment and CCTV coordination. Each specialist package had to fit the shop layout and the wider reopening programme.
The existing canopy was refurbished for the Engen conversion. Redundant canopy services were removed, the fascia and branded elements were coordinated, and Engen signage was introduced across the site.
These visible changes completed the public-facing side of the fuel station conversion Gauteng project, while the new fuel infrastructure and services carried the deeper operational change behind the new identity.

Electrical upgrades supported the forecourt, dispensers, shop equipment, signage, paypoint, turnstile and fuel systems. The wider scope also included coordination of refrigeration, air-conditioning, kitchen extraction and ventilation, as well as relocation of the generator.
The number of connected packages meant the retail fuel station project Jeff Masemola depended on careful project management.

The included coordination of building plans, a Site Development Plan request, fire inspections, drainage certification, ventilation certification and fuel-system pressure testing.
Contaminated-soil management associated with the forecourt works was also addressed during the project.
A brand conversion of this scale crosses several disciplines at once. Fuel storage and dispensing, forecourt construction, retail design, building services, branding, municipal processes and specialist certification all affect the same completion date.
THETA’s service station project management Pretoria role created one point of control across those workstreams. Its architectural, project-management and construction knowledge was supported by commercial oversight through Theta QS.

Are you planning a retail fuel station project a brand conversion or an upgrade to an existing service station in Gauteng?
THETA Projects provides architecture, project management, construction coordination and specialist fuel-retail experience for projects that need to move from an existing site to a completed, compliant and operational result.
Completed on 9 December 2025, the retail fuel station project Jeff Masemola delivered a fully converted Engen service station with new pump-and-tank infrastructure, a renewed forecourt, an upgraded shop, Café 365 requirements, refurbished canopy elements, Engen signage and coordinated building services.